Home solar permits in Thailand, MEA and PEA: steps, documents and fees (2026)

A Thai home that connects solar to its electricity supply must always apply to the utility for grid connection. In the MEA (the Metropolitan Electricity Authority, กฟน., which supplies Bangkok, Nonthaburi and Samut Prakan) area this goes through the MyEnergy system (myenergy.mea.or.th) with a single line diagram signed by a licensed electrical engineer; in the PEA (the Provincial Electricity Authority, กฟภ., which supplies the other 74 provinces) area it goes through PEA's channels, such as the PPIM system for homes selling power [1][2][3]. Most homes need no electricity business licence, because systems below 1,000 kVA are exempt, and no building permit, because rooftop panels weighing no more than 20 kg per square metre are not treated as a building modification [4][5].

Key facts

  • Every system connected to your home's supply needs a grid-connection application to MEA or PEA, even if you only use the power yourself [1].
  • The single line diagram must be signed by a licensed electrical engineer; systems up to 1 MW can be signed at associate engineer level [2].
  • The inverter must be on the utility's list; systems with more than 5 kW of inverter capacity need an export limiting device (EXL), and above 10 kW a routine test report [2].
  • Systems below 1,000 kVA need no ERC licence, and applying through the utility counts as notifying the ERC, under a notice in force since 4 April 2025 [4].
  • Ministerial Regulation No. 72 (2025) says rooftop panels weighing no more than 20 kg per square metre are not a building modification; a typical 625 W panel weighs about 10.7 kg per square metre [5][6][7].
  • Homes selling power in the PEA area pay a 2,140 THB inspection fee including VAT [3].

kWp is the peak capacity of the solar panels; kW is the size of the inverter or the system.

What you need, by type of home system

Requirement Self-use only Selling surplus Authority
Grid-connection application Required Required (with a sale application) MEA or PEA [1][3]
Diagram signed by an engineer Required Required Council of Engineers (engineer's licence) [2]
Inverter on the utility list Required Required MEA or PEA [2][8]
Export limiting device Per utility rules Required above 5 kW of inverter capacity MEA or PEA [2]
ERC notification (licence exemption) Through the utility application Through the utility application ERC [4]
ERC energy production licence (Por Kor 2) Not needed (below 200 kVA) Not needed (below 200 kVA) ERC [9]
Building modification permit Not needed if panels weigh ≤20 kg/m² Not needed if panels weigh ≤20 kg/m² District office, municipality or subdistrict administration [5][6]
Power purchase agreement and meter change Not needed Required MEA or PEA [3][10]

Permits step by step

Most installers handle these steps for you, but the documents carry the meter owner's name and signature.

  1. Check the meter and the roof. Confirm the meter owner and user type on your bill; if the name or address is wrong, correct it at the utility office first [3]. Have the installer assess whether the roof structure can carry the panels.
  2. Design the system and get the engineer's signature. The installer prepares a single line diagram for a licensed electrical engineer to sign, with a copy of the licence and a certificate of design and supervision [2].
  3. Choose listed equipment. The inverter must match the utility's list by brand, model and firmware and support Volt-Watt and Volt-Var control; systems above 5 kW of inverter capacity add a tested export limiting device [2]. In PEA areas, check smartlist.pea.co.th [8].
  4. Check building rules. A typical rooftop panel array is not a building modification if it weighs no more than 20 kg per square metre [5][6]. If you need a new steel frame or roof, ask the district office, municipality or subdistrict administration and have a civil engineer check it.
  5. Install the system to the signed design.
  6. Apply for connection. In the MEA area, apply through MyEnergy once installed [1]; in the PEA area, homes selling power apply through PPIM [3]. Grant recipients must apply by 31 August 2027 [11].
  7. Notify the ERC. Systems below 1,000 kVA are licence-exempt, and applying for design review and inspection through the utility counts as notifying the ERC [4]. PEA's process lists the ERC exemption notice as one step [3].
  8. Utility inspection and synchronisation test; homes selling power in the PEA area pay the 2,140 THB inspection fee [3].
  9. Meter change and start of supply. For homes selling power, the utility changes the meter and starts commercial operation [3][10].

Documents to prepare

MEA's list for homes selling power [2]:

Document Who prepares it
Copy of the meter owner's ID card, certified Homeowner
Single line diagram signed by an electrical engineer Installer
Copy of the engineer's licence and certificate of design and supervision Installer
Inverter datasheet and Q(U) and P(U) test reports Installer
Manual showing Volt-Watt and Volt-Var settings Installer
Bank account and email letter, with a copy of the passbook Homeowner
Power of attorney with a 30 THB stamp (if someone files for you) Homeowner
Export limiting device documents (above 5 kW of inverter capacity) Installer
Routine test report (inverter above 10 kW) Installer

In the PEA area, homes selling power must attach a bill or proof of user status dated within 3 months [3].

Fees and timelines

Item Amount or time Source
System inspection (selling, PEA area) 2,140 THB incl. VAT [3]
Connection fee (selling, PEA area) Amount not stated in the sources we read [3]
Stamp duty on a power of attorney 30 THB [2]
MEA fees Not stated in the sources we read [10]
Selected list published (selling, PEA area) Within 30 days of applying [3]
Fees and contract documents due Within 30 days of selection [3]
ERC response (systems not connected to MEA or PEA) 5 days after complete documents [4]

Engineering and filing are usually included in package prices: Synnex says it handles installation and permits, and HomePro says it plans and files permit applications [12][13]. Write into the contract whether utility fees are included.

Common reasons applications fail

  • Inverter or firmware not on the list: brand, model and firmware version must all match [2][14].
  • No export limiting device above 5 kW, or a device not on the tested list [2].
  • Engineer unlicensed or licence expired: the diagram is not accepted [2].
  • Meter owner name or bill details do not match: correct them at the utility first [3].
  • Fees not paid within 30 days: the buyback request is cancelled [3].

What changed most recently

  • 4 April 2025: the ERC's notice on notification of licence-exempt energy businesses took effect; systems below 1,000 kVA need no licence, and applying through the utility counts as notification [4].
  • 19 November 2025: Ministerial Regulation No. 72 (2025) was published in the Royal Gazette; rooftop panels weighing no more than 20 kg per square metre are not a building modification, replacing the earlier rule that capped area at 160 square metres and required a civil engineer's check [5][6].
  • 1 July 2026: buyback applications opened through MyEnergy and PPIM [3][10].
  • 18 September 2026: NEPC (the National Energy Policy Council, กพช., which sets energy policy) allowed households to install on the ground or on water as well as on roofs [15].

Frequently asked questions

Do I need a permit to install solar at home in Thailand?

You must apply to MEA or PEA for grid connection for any system connected to your home's supply, with a diagram signed by an engineer [1][2]. Most homes do not need an electricity business licence, because systems below 1,000 kVA are exempt [4], or a building permit, if the panels weigh no more than 20 kg per square metre [5].

How long does approval take?

The utilities do not publish a standard timeline that we could verify. In PEA's buyback process, the selected list is published within 30 days of applying, and fees are due within 30 days of selection [3]. After that, it depends on the local utility's queue for inspection and meter changes.

How much do permits cost?

Homes selling power in the PEA area pay a 2,140 THB inspection fee including VAT, plus a connection fee whose amount the sources we read do not state [3]. A power of attorney needs a 30 THB stamp [2]. The engineer's signature is usually included in the installer's package price; ask and put it in the contract.

If I only use the power myself, do I still need to tell the utility?

Yes. A system that runs in parallel with your home's supply needs a grid-connection application even if you do not sell power. MEA advises applying through MyEnergy once installed, with the extra buyback steps only if you want to sell [1].

Do I need a building permit from the district or municipality?

Usually not. Ministerial Regulation No. 72 (2025) says rooftop panels with a total weight of no more than 20 kg per square metre in any area are not a building modification [5][6]. A typical 625 W panel weighs about 10.7 kg per square metre [7]. If new structures are needed, ask the local authority first.

Who files the application, the installer or the homeowner?

Most installers file on the homeowner's behalf with a power of attorney signed by the grantor, the agent and two witnesses, with a 30 THB stamp [2]. The application remains in the meter owner's name. See 10 checks before you hire.

My system is already installed without approval. What now?

Ask an installer or electrical engineer to check whether the equipment is on the utility's list, then apply for connection through the same process. If the inverter is not listed, it must be replaced or submitted to the utility for testing and registration first [2]. An unapproved system cannot claim the tax deduction or sell power.

Back to top

Sources

  1. Thairath: MEA advice before installing rooftop solar; apply for connection through MyEnergy once installed. https://www.thairath.co.th/news/local/2968492 read 13 November 2026
  2. Thansettakij: selling power to MEA in 2026, equipment, documents and engineer licence levels. https://www.thansettakij.com/general-news/663189 read 13 November 2026
  3. Thansettakij: applying to PEA's 2026 programme via PPIM, steps, documents, 2,140 THB inspection fee. https://www.thansettakij.com/economy/energy/662928 published 2 July 2026, read 13 November 2026
  4. ThaiPublica: ERC exempts generation below 1,000 kVA from licensing; notification procedure B.E. 2568 in force from 4 April 2025. https://thaipublica.org/2025/05/erc15-05-2568/ published 15 May 2025, read 13 November 2026
  5. Yotathai: Ministerial Regulation No. 72 (B.E. 2568), dated 17 November 2025; rooftop panels up to 20 kg/m² are not a building modification. https://www.yotathai.com/yotanews/rule72-buildinglaw read 13 November 2026
  6. Thansettakij: government frees rooftop solar up to 20 kg from permits; earlier rule capped area at 160 m² with a civil engineer's check. https://www.thansettakij.com/economy/energy/626778 published 6 May 2025, read 13 November 2026
  7. HomePro: Home Solar 5 kW, RISEN 625 W panel, 227.9 by 113.46 cm, 27.8 kg. https://www.homepro.co.th/p/1256887 read 13 November 2026
  8. PEA: documents for registering an inverter product (smartlist.pea.co.th). https://smartlist.pea.co.th/storage/documents/9618/รายการเอกสารขอขึ้นทะเบียนผลิตภัณฑ์-Inverter.pdf read 13 November 2026
  9. Post Today: systems below 200 kVA need no Por Kor 2 licence. https://www.posttoday.com/smart-city/724148 read 13 November 2026
  10. PPTV: MEA's six steps to apply to sell power through MyEnergy. https://www.pptvhd36.com/news/%E0%B8%9B%E0%B8%A3%E0%B8%B0%E0%B8%8A%E0%B8%B2%E0%B8%AA%E0%B8%B1%E0%B8%A1%E0%B8%9E%E0%B8%B1%E0%B8%99%E0%B8%98%E0%B9%8C/278903 read 13 November 2026
  11. Ministry of Interior: Solar Phak Prachachon standard handbook, vol. 1, citizens' handbook, 2026 edition. https://peoplesolar.mea.or.th/assets/documents/project-handbook.pdf Published 27 October 2026, read 16 November 2026. News report: Thairath: Solar Phak Prachachon, apply for connection by 31 August 2027. https://www.thairath.co.th/news/society/2968816 published 28 October 2026, read 13 November 2026
  12. JIB: Synnex Solar Roof Solution handles installation, permits and advice. https://www.jib.co.th/web/product/readProduct/86300 read 13 November 2026
  13. HomePro: Home Solar, permit planning and filing service. https://www.homepro.co.th/p/1256865 read 13 November 2026
  14. Thansettakij: MEA advises checking the inverter's brand, model and firmware. https://www.thansettakij.com/economy/672156 published 24 October 2026, read 13 November 2026
  15. Government Public Relations Department, Office of the Prime Minister: NEPC meeting 3/2569 expands Solar Phak Prachachon to 10,000 MW. https://www.prd.go.th/th/content/category/detail/id/39/iid/542862 Published 18 September 2026, read 16 November 2026. News report: Post Today: NEPC allows households to install on the ground and on water. https://www.posttoday.com/smart-city/748946 published 18 September 2026, read 13 November 2026